We are well and busy.
We moved into the new chapel on
Tuesday. The workers were still working
on the wiring. Many members came to help load the truck. It went really well.
On Wednesday the contractor and
inspector debated the list of rework we wanted. The back steps were poured by
some members. The sink drains were
fixed. Well most of them. We put bolt locks on the doors.
Thursday we poured the front
steps. Just as the cement was floated
and finished, the piano arrived. We carried it through the back door. More
finish work was done by the contractors.
Friday the workmen finished the
front steps. They look pretty good. The wiring was finished. The lights outside
now are on at night. I got the computer to work again. A great brother has
built some storage boxes for the kids in primary that they can sit on during
classes. The building is almost finished. We now have closets for relief
society and primary and young men and women. There is even a cabinet for paper
goods and brooms.
Saturday, The youth practiced a
new song while workmen finished some projects.
Sunday we had the mission
President and his councilor and their wives for sacrament meeting. I t went well. We still need some room partitions in the
main hall to separate the classes. It is good to hear the primary children sing. We are planning the first activities for
this Saturday. The elders quorum plan on
building a bamboo fence between here and the neighbors. All are happy. This
will be good for this branch for a long time.
There is a typhoon coming
tonight and tomorrow. It will pass north of here. We will get the edge of it
with rain and wind. What a week.